ProjectsNusle · 64 m² · 7 weeks
Full gut renovation, Nusle apartment
Full gut-and-rebuild of the Nusle apartment (64 m²): strip-out and new fit-out, all-new electrics, water and drainage, structural wall and partition work, windows, bathroom and kitchen, ceilings, floors, tiling, paint, air conditioning, blinds, interior doors, and turnkey handover.

- 64 m²Size
- 7Weeks
- NusleLocation
Before / after
Same project. Documentation-grade shots, not a stock montage.
Full gut renovation, Nusle apartment
Brief
64 m² apartment in Nusle — the full unit. This was a full gut renovation: we stripped the old fit-out completely and rebuilt from the structure outward. Electrics, water and drainage were fully replaced, masonry walls and partitions were reworked, and we installed air conditioning and blinds alongside a single finish standard across the home, including the children's bedroom and master bedroom.
Scope
- Full interior strip-out within the apartment; protection of common areas; lawful waste removal
- Masonry and partition work to design — demolition, new blockwork, non-load-bearing moves, and chases for new services
- New electrical installation throughout — panel, circuits to design, cabling, sockets, switches, kitchen, lighting, and AC supplies
- New cold/hot water and drainage runs end-to-end; pressure tests and compliance paperwork
- Heating distribution adjusted or replaced on affected runs; connection to the building heat source
- Window replacement throughout, including sills and sealing
- Bathroom: waterproofing, tiling, sanitaryware, brassware, shower or bath, ventilation
- Bespoke kitchen: worktop, appliances, and utility hook-ups
- Gypsum suspended ceilings where designed — framing, service cut-outs
- Floor levelling, build-ups, and final finishes (timber / resilient / tile by room)
- Plaster, skim, and full interior paint including skirting and ceilings
- Air-conditioning installation including refrigerant runs and electrical hook-up per design and building rules
- Blinds (internal / window systems) — measure, install, and adjust
- New interior doors, frames, and ironmongery; light fittings, final clean, and client handover
Timeline
Survey: day 0. Quote: day 5. Contract: day 11. Start: day 22. Handover: week 7.